Cogeneration-Shandong
Time : 2020-04-27
Project description : Using pressure difference for generating, instead of previous temperature and pressure reducing device, high back pressure turbine.
Scope of supply : Steam turbine + Generator
Steam turbine model : B6-8.83/4.9
Main parameters : The steam pressure before the main steam valve of the steam turbine is 8.83Mpa, and the steam temperature before the main steam valve is 535°C. Exhaust pressure 4.9Mpa.